West Lane New Academic Building (Creative Humanities Hub)

Conceptual Design of the West Lane Academic Building (Creative Humanities Hub)

Construction works of the superstructure of the West Lane Academic Building (Creative Humanities Hub) began in January 2023. Concreting completed on 12th June 2023. Internal building services installation, interior fitting out works, underground utilities connection and backfilling works are in progress now in anticipation of handover for statutory inspections scheduled in December 2023.