Foundation works for the new academic building have commenced.
Updated Progress includes:
a) Building foundation piling work was completed on 3 May 2022 and the concrete blinding works of pile cap and tie beam works have commenced following the completion of the foundation works.
b) EVA (emergency vehicular access) foundation piling work reported completion on 22 August 2022, the pile loading test for Building Department inspection was being arranged.
c) Tree transplant works were completed on 27 June 2022 and planters to retain the transplanted trees were completed on 24 August 2022.