Lift modernization works for the three lifts at M Building have commenced since 4 September 2020. The works for lift no. 3 and 2 were completed and the lifts resumed normal operation on 14 December 2020 and 24 March 2021 respectively. Upon its completion, items upgraded/added are as below:
a. Enhanced safety system along the lifting mechanism.
b. Replaced with energy efficient motor.
c. Additional infra-red sensor at door closing system.
d. Additional intercom system.
e. Enhanced hall button panel, lift operating panel and position indicator.